Thomas,
Agreed. We don’t want to put too many gasifiers in the North Pole and add to melting the icecap. Denmark would become like Miami.
Competitive in today's markets to me means a target price of $3-5/kWe for the complete system. $4-6/kWe should work where you also have heat production as at UBC. Is it possible? It is clearly difficult but we will continue to try to design and develop affordable systems.
Tom
TK>Tom -
My comments to the different gasifiers are written below each.
But before any thing will be commercial it must be competitive - with out enormous green premiums.
The very few markets on the north pole and pacific islands etc will never drive the development alone.
Thomas
--------
Thomas
Who are the likely small scale gasifier suppliers that will conquer these challenges?
A
Ankur Scientific, India http://www.ankurscientific.com/ Too bad workman ship - hot parts made from refractory steel - large char loss and too much tar in the gas for larger ones - only for developing countries.
B.
Babcock Volund, Denmark http://www.volund.dk/
3 gasifiers up to 2 MWe
Too expensive and complex - the real price level seems to be 0,4-0,6 us$/kWh
Biogen, Dominican Republic http://www.biogendr.com/app/en/frontpage.aspx
300-500 kWe modules, Italy
Dont know
C
CarboConsult, South Africa http://www.carboconsult.com/
250 kWe, Melanie, Gauteng, South Africa Dont know
Carbona/Andritz, Finland
http://www.andritz.com/pp-gasification-andritz-carbona
3 MWe plant in Skive, Denmark
Fluidised bed gasifier are too complex and produce a dirty gas - needs pellets
CleanStGas, Austria http://www.cleanstgas.com/
125-250 kWe/235-480 kWth
Dont know
Community Power Corporation www.gocpc.com
50-75 kWe modules.
Dont know
E
EKZ, Switzerland www.ekz.ch
Turnkey wood gasifier installations
Dont know
G
Gasek, Finland www.gasek.fi
50 kWe/100 kWth
Too small to be competitive
I
IISc, India and Licensees
http://cgpl.iisc.ernet.in/site/Technologies/BiomassGasification/tabid/68/Def
ault.aspx
M
MEVA Innovation AB, Sweden (fine wood fuels) http://www.mevainnovation.se/
1-10 MWe; 1.2 MWe in construction Horlax, Pitea
Mothermik, Germany http://www.mothermik.com/engl/prod-1holzver-e.html
10 plants.250 kWe
Too big char loss and too high maintenance cost
N
Nexterra Ltd., Vancouver, Canada http://www.nexterra.ca/
2 MWe in construction. University of British Columbia
R
Repotec, Austria http://www.repotec.at/index.php/homepage.html
Dual fluidized bed for CHP
Too complex and expensive
S
Satake, Japan (IISc, India technology)
http://www.satake-group.com/news/2008/080214.html
Up to 900 kWe modules
Stirling DK, Denmark http://www.stirling.dk/
15-140 kWe, Updraft gasifier with stirling engine.
Far too expensive and to small to be reliably investment cost 10000 €/Kw
T
TK Eenergi, Denmark http://www.tke.dk
3 stage gasifier
Too complex and too difficult to upscale - most ly due to bed stability issues U Urbas Energietechnik, Austria http://www.rsbiomass.com/urbas_gas.html
150 kWe/310 kWth fixed bed downdraft
W
Weiss, Denmark, two stage gasification www.weiss-as.dk
1-2 MWe
Wrong desing - can not be safety approved due to hot metalic parts - Hot grid not stable - Impossible to get reliably informations about
X
Xylowatt, Belgium http://www.xylowatt.com/
350 kWe modules
Nice design - probably the best gasifier
XyloPower AG, Switzerland www.xylopower.com
Dont know
Which companies have 3 operating, commercial, gasifiers?
Who else?
Tom Miles
-----Original Message-----
From: gasification-bounces at lists.bioenergylists.org
[mailto:gasification-bounces at lists.bioenergylists.org] On Behalf Of Thomas Koch
Sent: Monday, June 25, 2012 2:15 PM
To: Discussion of biomass pyrolysis and gasification; mark at ludlow.com
Subject: Re: [Gasification] 2 MWe Gasifier at University of British Columbia, Vancouver, Canada
Tom
I am sure this price level is achieveable - BUT BUT BUT - there is a major challege that must be overcommed.
You need some where you can have 5-10 similar gasifiers operating for 10 of thousans of hours each with in reachable distance from their "parent (s)"
and this alone needs 50 - 100 mio $ on top of the market price for the electricity - and it is possible to maintain a stable and bright and not religious brain capacity for a decade or two.
On top of that you need to start with a good idea and that is where most principles fail.
And what does that mean?
Not too complex - with a potential to handle the challenges that will come in an ECONOMICALLY COMPETITIVE way!!!
Examples - Vølund - Nexterra - CFBs-Repotec and this type of gasifiers will alvays have the challenge og tar/perticle gas handling issues - personally I believe it is too complex to handle in a competitive way.
FCC - may be large scale - but catalyst and gasifier is a challenge
2-3 stage - Viking - double feuer - TKE - and the likes have high temperature challenges and reduction challenges and bed stability issues - variation in gaspermeability etc Stirling show a large drop in efficiency if upscaled above 50-75 kW thus the biomass handling systems becomes very small and sensitive.
Entrained flow are very big and needs extensive pretreatment of the fuel.
Many things will work for some time if nursed properly by the enthusiastic developers.
Thomas
-----Oprindelig meddelelse-----
Fra: gasification-bounces at lists.bioenergylists.org
[mailto:gasification-bounces at lists.bioenergylists.org] På vegne af Tom Miles
Sendt: 25. juni 2012 22:51
Til: 'Discussion of biomass pyrolysis and gasification'; mark at ludlow.com
Emne: Re: [Gasification] 2 MWe Gasifier at University of British Columbia, Vancouver, Canada
Thomas,
You seem to be the bearer of good news.
Can you deliver a (3 stage) gasifier(s) to deliver 2 MWe to a grid in Alaska? What would you expect the capital and operating costs to be?
We have a few small communities with electrical loads of 1-2 MWe. Power is currently supplied from diesel generators for USD $0.44-$0.65/kWh. Good clean wood chips are available at $40-50% MC and $USD 85-100/dry ton. #2 heating oil costs about $4.40 or about $32/MMBtu (HHV). Most communities just want to produce power. Heat distribution does not exist but they could probably sell heat in a small loop for about $20/MMBtu. Is there a future for gasification in these communities?
Thanks
Tom Miles
_______________________________________________
Gasification mailing list
to Send a Message to the list, use the email address Gasification at bioenergylists.org
to UNSUBSCRIBE or Change your List Settings use the web page http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenerg
ylists.org
for more Gasifiers, News and Information see our web site:
http://gasifiers.bioenergylists.org/
_______________________________________________
Gasification mailing list
to Send a Message to the list, use the email address Gasification at bioenergylists.org
to UNSUBSCRIBE or Change your List Settings use the web page http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenerg
ylists.org
for more Gasifiers, News and Information see our web site:
http://gasifiers.bioenergylists.org/
_______________________________________________
Gasification mailing list
to Send a Message to the list, use the email address Gasification at bioenergylists.org
to UNSUBSCRIBE or Change your List Settings use the web page http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenergylists.org
for more Gasifiers, News and Information see our web site:
http://gasifiers.bioenergylists.org/
_______________________________________________
Gasification mailing list
to Send a Message to the list, use the email address Gasification at bioenergylists.org
to UNSUBSCRIBE or Change your List Settings use the web page http://lists.bioenergylists.org/mailman/listinfo/gasification_lists.bioenergylists.org
for more Gasifiers, News and Information see our web site:
http://gasifiers.bioenergylists.org/
More information about the Gasification
mailing list