G'day Vianney,

 

For 30 kW you are probably looking at Chinese or Indian technology as
"western" companies only think BIG (I may be wrong). Capstone micro-turbines
may fit the bill though. What may be useful is to have 2-3 smaller units
(actually Fiat used to supply one based on a Fiat 500cc engine I think) so
you can adjust to gas production but still run at near full load (and you
have a standby if one fails.

 

All the best,

HOOROO

 

Mr. Paul Harris, Room 202 Charles Hawker Building, Faculty of Sciences, The
University of Adelaide, Waite Campus, PMB 1, Glen Osmond SA 5064 Ph    : +61
8 8303 7880      Fax   : +61 8 8303 4386
<mailto:paul.harris at adelaide.edu.au> mailto:paul.harris at adelaide.edu.au
<http://www.adelaide.edu.au/directory/paul.harris>
http://www.adelaide.edu.au/directory/paul.harris

 

CRICOS Provider Number 00123M

This email message is intended only for the addressee(s) and contains
information that may be confidential and/or copyright.  If you are not the
intended recipient please notify the sender by reply email and immediately
delete this email. Use, disclosure or reproduction of this email by anyone
other than the intended recipient(s) is strictly prohibited. No
representation is made that this email or any attachments are free of
viruses. Virus scanning is recommended and is the responsibility of the
recipient.

 

From: digestion-bounces at lists.bioenergylists.org
[mailto:digestion-bounces at lists.bioenergylists.org] On Behalf Of Vianney
Tumwesige
Sent: Wednesday, 13 July 2011 7:19 PM
To: For Discussion of Anaerobic Digestion
Subject: [Digestion] Goat and sheep to power an Abattoir

 

Hello AD friends, 

How all is well. I got a call today from an abattoir, they are looking at
Generating biogas from 2000-2500 goats/sheep intended to be slaughtered per
day. My system estimates 4.8 tons of waste every day, this is expected to
generate 300 cubic metres of biogas hence I estimate 30kw.

What size of a biogas driven generator would i need to get the job done?
Where can I find this generator and at what cost?

Thanks

-- 
Vianney Tumwesige

Director - Green Heat (U) Ltd   Picture
<http://c/photos/public/AIbEiAIAAABECOv50_eundi67QEiC3ZjYXJkX3Bob3RvKigwYzZm
Y2VhNzIxN2U0MzAxZDgzMjIzMjQwMTIyYjc4NmIxZDIyZTVkMAEoE3_PbMYF3svhn4g5QGXXnlOr
Rw> 
P.O. Box 10235
Kampala-Uganda
256 (0) 71 237 9889


"The more people are self sufficient in cooking fuel, the more personal and
financial freedom they have." - Emma Casson


 <http://trustvianney.wordpress.com/> 


 

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.bioenergylists.org/pipermail/digestion_lists.bioenergylists.org/attachments/20110714/64a5b56f/attachment.html>


More information about the Digestion mailing list