Hi Krishna,
The plant has a 42-45 day HRT (the climate can be a bit cool), and the total solids are about 8%. That initial start up was slow because we resisted adding cow manure, but now the methane content of the biogas is just above 60%. The plant onlt has about 4 months installed, so we hope to have a more detailed profile later.
Cheers
Sent via BlackBerry by AT&T
-----Original Message-----
From: Murali Krishna <bmkrishna6 at gmail.com>
Sender: "Digestion" <digestion-bounces at lists.bioenergylists.org>
Date: Fri, 28 Jun 2013 15:25:43
To: For Discussion of Anaerobic Digestion<digestion at lists.bioenergylists.org>
Reply-To: For Discussion of Anaerobic Digestion
<digestion at lists.bioenergylists.org>
Subject: Re: [Digestion] Biogas plant at Zoo
_______________________________________________
Digestion mailing list
to Send a Message to the list, use the email address
Digestion at bioenergylists.org
to UNSUBSCRIBE or Change your List Settings use the web page
http://lists.bioenergylists.org/mailman/listinfo/digestion_lists.bioenergylists.org
for more information about digestion, see
Beginner's Guide to Biogas
http://www.adelaide.edu.au/biogas/
and the Biogas Wiki http://biogas.wikispaces.com/
More information about the Digestion
mailing list