[Gasification] GRETHA starts construction of 4 MWth (1MWel) DFB (dual fluidized bed) steam gasifier in Nong Bua, Thailand and signs contract for additional 4 MWth gasifier for Japan
Tom Miles
tmiles at trmiles.com
Mon Feb 23 09:29:20 CST 2015
GRETHA starts construction of 4 MWth (1MWel) DFB (dual fluidized bed) steam
gasifier in Nong Bua,Thailand and signs contract for additional 4 MWth
gasifier for Japan
Leopold Nenning
<https://www.linkedin.com/profile/view?id=99279188&goback=%2Egde_2401449_mem
ber_5971265172927430657> Technical Manager, GREG; Licensed Architect
(Austria) Top Contributor
Güssing Renewable Energy Thailand (GRETHA) will build this first DFB biomass
gasifier in Asia with engineering support of GP Green Energy of India.
Manufacturing of key components has started.
Feedstock for both projects will initially be wood chips while design allows
for gradually mixing MSW fractions This is a big step for GRETHA, and its
Austrian sister GREG (Güssing Renewable Energy GmbH) and their parent
company CaRe.
The plants represent the latest version of indirect gasification as
developed at VUT (Vienna University if Technology) and first demonstrated at
the plant in Güssing, Austria (owned by BKG, another sister company of
GRETHA).
https://lnkd.in/bBAJZKj
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://lists.bioenergylists.org/pipermail/gasification_lists.bioenergylists.org/attachments/20150223/7c3d67d1/attachment.html>
More information about the Gasification
mailing list